LOAN NO.: 2983-CAM
Executing Agency: Ministry of Public Works and Transport
Nature of Contract: Construction
Contract No.: PMU/MPWT/SECTDP/ICB/CW-05
Contract Description: Improvement/rehabilitation of National Road No. 1 From 159 Km to 165 Km (6.14km) - Bavet Urban Road (ICB/CW-05)
The Works consist of Improvement/Rehabilitation of National Road No. 01 from 159th KM to 165th km - Bavet Urban Road Section (6.14Kms) Indicative quantities are:
• Asphalt Concrete -6,600m3
• Road Earth Works-57,500m3
• Aggregate Base Course-40,000m3
• Reinforced Concrete Pipe works-12,300m
• Concrete Works-3,100m3
• Street Lightings -140Nos
• Foot Walk Slab Pavings -24,000m2