Print

DAM FOR FLOOD CONTROL ON THE OLONA RIVER
Details
Locations:Italy
Start Date:Jan 1, 2007
End Date:Dec 31, 2010
Sectors: Mapping & Cadastre, Research, Water & Sanitation
Description
The project concerned the realisation of a dam on the Olona River, aiming to protect the surrounding areas from flooding.
SGI has been particularly engaged to carry out the following activities:
- Works supervision and coordination of geognostic and geotechnical surveys;
- Technical support for the realisation of water resistance tests;
- In situ quality control and testing of works and materials..
Moreover SGI has been awarded the works supervision on the third lot.
Following are listened the key features of the dam:
- Dam catchment area: 97 km2
- Dam crest : 1600 m
- Total storage capacity : 1,790,000 m3