WWTP Skenderaj
Details
Locations:Kosovo
Start Date:Jan 1, 2005
End Date:Dec 31, 2007
Sectors: Water, Sanitation & Hygiene
Description
New construction of a mechanic/biologic WWTP for removal of the organic matters BOD5 and COD by IMMHOFF-Tank and trickling filter withsimultanes aerobic sludge stabilization.
Scheduled Technique:
Sewage treatment: intake pump station, compact unit with screens and an aerated grit and grease chamber, Immhoff-Tank, trickling filter, secondary settling tank
Sludge treatment: Sludge treatment by cold digestion in Imhoff-Tank, gravity thickening and sludge drying beds
Activities:
Complete design and engineering of a mechanic/biologic WWTP and a new construction of a transport sewer for the EAR contractor the JV Dywidag-MASS.
- 2006 Process- and hydraulic design for the WWTP
- 2006 Hydraulic- and technical design for the transport sewer, 3.5km, DN 400 to DN 600
- 2007 Technical and detailed design for technological part, constructive part, electrical and
SCADA part and HVAC part.
Client: EAR European Agency for Reconstruction.
Project Manager: Dipl.-Ing. J. Krone.
Final Size: 8,000 PE.
Commissioning:2007.
Contract: Design-build contract according to EU conditions of contract.
Finance: EAR European Agency for Reconstruction.
Projektkosten: 4,000,000 €.