Plant Design, Supply and Installation of 220/132/33 kV Chilime Hub New GIS (Part-I) and 220(Hybrid)/132/33 kV Trishuli-3B Hub New AIS (Part-II) under 220 kV Chilime-Trishuli Transmission System (Package II)

Last update: May 9, 2019 Last update: May 9, 2019

Details

Locations:Nepal
Start Date:Nov, 2017
End Date:May, 2019
Contract value: USD 14,008,306
Sectors:Civil Engineering, Electrical Engineering
Civil Engineering, Electrical Engineering

Associated funding

Associated experts

Description

Reference number: ICB-CHTHSS– 073/74-01
Title: 220kV Chilime-Trishuli Transmission System Project
Description: Design, Supply and Installation of 220/132/33 kV Chilime Hub New GIS (Part-I) and 220(Hybrid)/132/33 kV Trishuli-3B Hub New AIS (Part-II) under 220 kV Chilime-Trishuli Transmission System Project (Package II)
The main components of the Project include:
a. Design, Supply, Installation and Construction of a 220/132/33kV, 7*53.33 MVA & 132/33 kV, 50MVA GIS Substation at Chilime Hub and 220/132/33kV, 7*53.33 MVA & 132/33 kV, 50MVA Hybrid (AIS) Substation at Trishuli 3B Hub.
b. Design, Supply, Installation and Construction of 220kV and 132 kV line bays and other associated works.
c. Supply and installation of Communication equipment including Remote Terminal Units (RTU), Power Multiplexers (MUX) and necessary communications works at the Substations.

Duration: 18 Months