AMMAN SOLID WASTE MANAGEMENT
Details
Locations:Jordan
Start Date:Unknown
End Date:Unknown
Contract value: JOD 2,681,386
Sectors: Civil Engineering, Pollution & Waste Management (incl. treatment)
Description
Construction of the Third Cell at the Existing Ghabawi Landfill, Amman, Jordan
The scope of work is as follows:
i. Earthworks: Excavation, construction of side-slope embankments, grading and compaction, approximately 500,500 m3 as cut and 46,100 m3 as fill. The total surface area of Cell # 3 is 110,200 m2;
ii. Supply and installation of Geosynthetics including HDPE Geomembrane, GCL, Protection Geotextile, Filtration Geotextile, and HDPE Geopipes;
iii. Construction of leachate collection system, as follows:
a. D 160 mm geopipe (inside diameter) approximately 955 m.
b. D 280 mm geopipe (inside diameter) approximately 1255 m.
c. D 400 mm geopipe (inside diameter) approximately 190 m.
iv. Reshape and restoration of the existing Cell # 1 grades and lining repair. Approximately moving 50,000 m3 of waste;
v. Quality assurance and quality control; and
vi. Production of As-Built Drawings and As-Built work file.