Other

11-385 BARC

Last update: Jun 25, 2015 Last update: Jun 25, 2015

Details

Locations:India
Start Date:Unknown
End Date:Dec 31, 2005
Sectors:Water & Sanitation
Water & Sanitation
Categories:Goods, works, consulting services
Funding Agencies:
Date posted:Apr 25, 2013

Associated funding

Associated experts

Description

KEY STAFF

Project Director M. Rognoni
Project Manager P. Lucchi
Process Manager A. Trezzi
Chief Designer A. Trezzi
Quality Controller D. Quaranta

PROCESS

Water to be treated

Total Design Capacity 50 t/d
Number of units 1×100%
Guaranteed TDS 0.5 ppm achieved either with SED
Process Arrangement MVC (Mech. Compressor by Piller) two effects
Tubes material Titanium
Shell material AISI 316L Stainless steel
Tubes fixing Rubber grommets
Top Brine Temperature 65°C.

Scope of work
Turn-key

Notes:

Distillate guarantee 0.5 ppm ensured by SED
One spare set of Al 5052 tubes are supplied for alternative test run.
Energy absorption = 8.5 kW/ton

Want to unlock full information?
Member-only information. Become a member to access projects awards, find the right consortia partners, subcontractors and more.