Camerron U.S. Consulate Building
Details
Locations:Cameroon
Start Date:Jan 1, 2004
End Date:Sep 30, 2005
Sectors: Electrical Engineering
Description
Employer : Caddell.
Construction Area : 13.500 m2
The scope of supply of the U.S.A. Embassy in Cameroon, built by the OBO department of the U.S.A. State Ministry consists of electrical installation works based on turn-key delivery of preparation of the execution drawings and material BOQ, acceptance procedures, installation, commissioning, client acceptance tests. This project has been executed with total compliance to the American standards and with compliant material. In this project, 90 km galvanized electrical steel pipe, 300 km single wire cable with various section, 2200 pieces of lighting fixture, 1750 pieces power outlets, 12 SM fibre optic input with 900 points telecom system, fire alarm system, anouncement and security system, outdoor and indoor lighting installation have been realized.