Print

Manzini Region Water Supply System, Lot 1
Details
Locations:Eswatini (Swaziland)
Start Date:Jul 31, 2023
End Date:Jan 29, 2025
Contract value: SZL 373,807,069
Sectors: Civil Engineering, Water & Sanitation
Description
Name of Project: Manzini Region Water and Sanitation Project
Lot Number & Name: Construction of Raw Water Pumping Main, Water Treatment Plant and Treated Main – Lot 1
Summary of Scope of Contract: The Construction of Manzini Region Water Supply System Lot 1. The works entail the construction of an Intake Pump Station, Raw Water Transmission Main (900m of DN800 DI), Staff Houses (16Nos. two bedrooms - 2No. one-storey blocks, 8Nos one bedrooms - 1No. One storey blocks), New Matsapha Water Treatment Plant, Treated Water Pump Station, Treated Water Rising Main (6,000m of DN500 DI)
Contract Duration: 548 days