World Bank HQ

Solar Energy and Access Project: Construction de la Ligne de raccordement entre le site de la centrale solaire de Kouritenga et la ligne existante (3km) double terne en coupure d’artère

Last update: May 6, 2025 Last update: May 6, 2025

Details

Locations:Burkina Faso
Start Date:Sep 25, 2024
End Date:Mar 25, 2026
Contract value: EUR 1,184,538
Sectors:Civil Engineering, Electrical Engineering
Civil Engineering, Electrical Engineering
Categories:Works
Funding Agencies:
Date posted:May 6, 2025

Associated funding

Associated experts

Description

Project: P166785-Solar Energy and Access Project

Bid/Contract Reference No: BF-UGP/SOLEER -398533-CW-RFB

Scope of Contract: Construction de la Ligne de raccordement entre le site de la centrale solaire de Kouritenga et la ligne existante (3km) double terne en coupure d’artère

Duration of Contract: 18 Month(s)