Description
The existing HD-steam boiler in the Burghausen Refinery has to be equipped with blending burners oil/gas. Based on an existing study all necessary actions have to be elaborated within a feasibility study. FEED services will be offered on an optional basis.
Technical data:
Steam capacity: 20 / 110 t/h
Pressure: 53 / 62 bara
Temperature: 375 / 400°C
Total power of dual fuel burners: 95 MW
ILF Sevices:
Project Management
Site survey
Evaluation of different options for natural gas supply
3D Model design in PDS
PID's in SPPID
HAZOP
Functional requirements for control system
Tender for 3 LLI's incl. recommendation to award the contract.