Crystal Gas Plant Etzel - EPCM
Details
Locations:Germany
Start Date:Jan 1, 2009
End Date:Dec 31, 2013
Sectors: Civil Engineering, Energy, Procurement
Description
EDF and EnBW ordered to construct the CRYSTAL gas storage facility at Etzel (Germany) for gas trading purposes and have signed a cavity lease agreement with IVG for four salt caverns with the potential for future extension. The gas plant is designed with two production trains of electrical driven turbo gas compressors operating in parallel. For gas withdrawal from the caverns, two production trains with gas preheating, pressure reduction and glycol dehydration facilities are foreseen.
Technical data:
4 salt caverns of 650,000 m3 each
Total working gas capacity: approx. 351 m Nm³
2 production trains: 2 x 50%
Gas injection rate: max. 300,000 Nm3/h
Gas withdrawal rate: max. 600,000 Nm3/h
Option for plant extension: +4 caverns, +2 trains
Gas plant operation time: 35 years
Services:
Tender design
Detailed design
Construction management
Commissioning.
Client: EDF Gas Division, Energie Baden-Württemberg AG.