Description
Client: General Directorate for Dams and Water Reservoirs -Erbil
Project Description:
The proposed earth dam is to be located in the Shewasoor Valley, in the Kurdistan Region of Iraq. The dam receives rainfall from a catchment area of approximately 104 km2 with total live capacity equals to 6.7 million m3 (MCM) and dead capacity of 0.75 MCM over a useful life of 390 years.
he maximum spillway discharge for this proposed dam is 157.5m3/s. The total height of the dam is 34 m at its highest level and 10 m width for the crest. The down- stream side is of slope 1: 2.75, while the up-stream side of dam is of slope 1: 3.0 protected with concrete blocks.
The core is extended to rock layer as a cutoff, while 1.5m thick blanket of same core materials is placed at upstream side of the dam to length of about 250m into reservoir.
Services Provided
Review the geological and geophysical studies for the dam location and the hydrological study for the catchment area.
Review the Report of the surveying works.
Review the Hydraulic design works for the dam, the spillway and conveyance system.
Review of the Stability analysis for the dam.
Review the specification of the dam.
Project Description:
The proposed earth dam is to be located in the Shewasoor Valley, in the Kurdistan Region of Iraq. The dam receives rainfall from a catchment area of approximately 104 km2 with total live capacity equals to 6.7 million m3 (MCM) and dead capacity of 0.75 MCM over a useful life of 390 years.
he maximum spillway discharge for this proposed dam is 157.5m3/s. The total height of the dam is 34 m at its highest level and 10 m width for the crest. The down- stream side is of slope 1: 2.75, while the up-stream side of dam is of slope 1: 3.0 protected with concrete blocks.
The core is extended to rock layer as a cutoff, while 1.5m thick blanket of same core materials is placed at upstream side of the dam to length of about 250m into reservoir.
Services Provided
Review the geological and geophysical studies for the dam location and the hydrological study for the catchment area.
Review the Report of the surveying works.
Review the Hydraulic design works for the dam, the spillway and conveyance system.
Review of the Stability analysis for the dam.
Review the specification of the dam.