Water and Electricity Production and Distribution Board /Régie de Production et de Distribution d’eau et d’électricité

BI-Jiji and Mulembwe Hydropower - P133610

Last update: 2 days ago Last update: 25 Apr, 2024

Details

Project End Date:2026-06-30
Location:BurundiBurundi
Category:Goods, Works, Consulting services
Status:Completion and evaluation
Sectors:Energy
Languages:English
Contracting Authority Type:Government / Public Sector
Eligibility:Unknown
Budget:USD 270,400,000
Date posted:06 Dec, 2013

Attachments 7

Associated Awards

Project cycle timeline

STAGES
EARLY INTELLIGENCE
PROCUREMENT
IMPLEMENTATION
Cancelled
Status
Programming
Formulation
Approval
Forecast
Open
Closed
Shortlisted
Awarded
Evaluation

Associated tenders 2

Status

Date

Description

Updated on January 5th 2015:

The objectives are to: (a) develop two run-of-river hydropower sites at Jiji and Mulembwe; and (b) construct a transmission line from Jiji to Bujumbura that will provide reliable electricity supply and displace expensive thermal generation. The grant was signed on 18 July 2014. Environmental Assessment Category A. Project: P133610. US$ 99.9/22.0/36.6/95.0 (IDA Grant/AFDB/ECEU/EUIB). No consultants are required. REGIDESO (Régie de Production d’Eau et d’Electricité), BP 660, Bujumbura, Burundi, Tel: (257-2) 225-7445, Fax: (257-2) 222-6563, E-mail: nyctekfrance@yahoo.fr, Contact: Mr. Libérat Mfumukeko, Director General
-----------

Updated on October 27th, 2014:

The objectives are to: (a) develop two run-of-river hydropower sites at Jiji and Mulembwe; and (b) construct a transmission line from Jiji to Bujumbura that will provide reliable electricity supply and displace expensive thermal generation. Bank Approval completed on 22 April 2014. Environmental Assessment Category A. Project: P133610. US$ 99.9/22.0/36.6/95.0 (IDA Grant/AFDB/ECEU/EUIB). No consultants are required. REGIDESO (Régie de Production d’Eau et d’Electricité), BP 660, Bujumbura, Burundi, Tel: (257-2) 225-7445, Fax: (257-2) 222-6563, E-mail: nyctekfrance@yahoo.fr, Contact: Mr. Libérat Mfumukeko, Director General
-------------

Updated on August 5th, 2014:

The objectives are to: (a) develop two run-of-river hydropower sites at Jiji and Mulembwe; and (b) construct a transmission line from Jiji to Bujumbura that will provide reliable electricity supply and displace expensive thermal generation. Bank Approval completed on 22 April 2014. Environmental Assessment Category A. Project: P133610. US$ 99.9/22.0/36.6/95.0 (IDA Grant/AFDB/ECEU/EUIB). No consultants are required. REGIDESO (Régie de Production d’Eau et d’Electricité), BP 660, Bujumbura, Burundi, Tel: (257-2) 225-7445, Fax: (257-2) 222-6563, E-mail: nyctekfrance@yahoo.fr, Contact: Mr. Libérat Mfumukeko, Director General
---------------

The objectives are to: (a) develop two run-of-river hydropower sites at Jiji and Mulembwe; and (b) construct a transmission line from Jiji to Bujumbura that will provide reliable electricity supply and displace expensive thermal generation. Preparation is underway. Environmental Assessment Category A. US$ 70.0/70.0 (IDA Credit/EUIB). Consultants will be required. REGIDESO, BP 660, Bujumbura, Burundi, Tel: (257-2) 222-3412, Fax: (257-2) 222-6563