Fruit Tree Productivity Project
TC-1A: Consultant to conduct technical feasibility studies and Strategic Environmental Assessment for perimeters in rain-fed area
Awarded to: Groupement CID, SCET/SCOM, ADI and CRC/SOGEMA
Date of the contract: May 14th, 2008
Duration: 60 months
Amount: $ 18 712 269
TC-1B: Consultant to conduct technical feasibility studies and Strategic Environmental Assessment for perimeters in irrigated area
Awarded to: Scet Scom/ CID/ADI/AHT Group AG/CRC Sogema
Date of the contract: October 20th, 2008
Duration: 60 months
Amount: $ 18 949 079
TC-3A-P: Contractor to conduct land preparation earthworks, tree planting and Orchard care and maintenance for rain fed areas
Awarded to: Consortium Boughlala - Doughmi
Date of the contract: March 4th, 2009
Duration: 24 months
Amount: $ 9 327 737
TC-2A: Assessment of training needs for staff of the MAPM and elaboration of training program
Awarded to: SIS Consultants
Date of the contract: September 5th, 2009
Duration: 04 months
Amount: $ 143 687
TC-3A1: Contractor to conduct preparation earthworks for rain fed areas
Awarded to: Ets. Ahouzi (Lot 1); Société Sellam Azouz (Lot 3); Ornos (Lot 5); Etb. Boujemaa (Lot 6)
Date of the contract: January 1st, 2009
Duration: 30 months
Amount: $ 33 071 831
TC-3B1: Irrigation infrastructure works in the Chichaoua region
Awarded to: SNCE (lots 1, 3); SOGETRAMA (Lot 2); STAIP (lot 4)
Date of the contract: February 6th, 2010
Duration: 18 months
Amount: $ 31 487 980
TC- 5A: Training, technical assistance and support to beneficiaries, professional organizations and operators in olive, almond and figs value chain
Awarded to: UNOPS
Date of contract: April 29, 2010
Duration: 42 months
Amount: $ 17 612 306
TC-3A1-Bis Olive trees: Extension work of olive tree planting in rain fed areas
Awarded to: Gpmt DAGHMI Agri (Lot 1); Sté AJARDIN (lot 2); JEHNI Mohamed (Lot 3); Gpmt OUENZAR (Lot 4)
Date of the contract: April 29, 2010
Duration: 24 months
Amount: $ 9 116 290
TC-3A1-Bis Almonds: Extension work of almond tree planting in rain fed areas
Awarded to: BOUGHLALA Mustapha (Lot 1); Grpt OUENZAR-BERRAHO Abdelmalki (Lot 2)
Date of the contract: July 26, 2010
Duration: 24 months
Amount: $ 4 767 650
TC-5B: Training, technical assistance and support to beneficiaries, professional organizations and operators in date palms value chain
Awarded to: Gpt AFC-Agriconsulting-EuroConsultants
Date of contract: July 26, 2010
Duration: 40, 5 months
Amount: $ 8 193 078
TC-3A2.1: Olive tree planting in rain fed areas
Awarded to: Gpt ORNOS & Almudeyne (Lots 1-2-6-8), Gpt GIE OLEASERVICES, CBH Agro & SODEOM(Lots 3& 5), Entreprise BOUGHLALA Mustapha (Lots 4-7)
Date of contract: September 13, 2010
Duration: 24 months
Amount: $ 26 540 090
TC-6A1: Supply of date palm plants
Awarded to: Sté QUALIAGRO (Lot 1); Laboratoire ISSEMGHY Biotechnologie (Lot 2)
Date of contract: September 30 , 2010
Duration: 3 years
Amount: $ 7 577 580
TC-3A2.2: Extension of Olive tree planting
Awarded to: Sté FITONOVO (Lot 1, Lot 3, Lot 4, Lot 5, Lot 7, Lot 8), Ets Mohamed AHOUZI (Lot 2), ORNOS AL Mudayene (Lot 6, Lot 9, Lot 10),
Date of contract: September 30, 2010
Duration: 24 months
Amount: $ 26 656 130
TC-3A2.3: Extension of almond tree planting
Awarded to: TAIBI BOUJAMAA
Date of contract: September 30, 2010
Duration: 24 months
Amount: $ 1 824 690
TC-2B: Capacity building of MAPM staff related to project implementation
Awarded to: Gpmt AFC/Coach/IFG/Interp
Date of contract: December 20, 2010
Duration: 18 months
Amount: $ 2 203 736
TC-3 B2: Irrigation infrastructure works
Awarded to: SOGETRAMA (Lot 1,Lot 2); SNCE ( Lot 3, Lot 4, Lot 9); Sté Ben Mimoune (Lot 5, Lot 6); Gpmt Moulin TP/ Bouabid (Lot 7)
Date of contract: December 23, 2010
Duration: 18 months
Amount: $ 33 236 541
TC-6 A2: Works of cleaning bundles of date palm tree for farmers in oasis areas
Awarded to: ARIG TRAVAUX ( Lots 2, 4 & 5)
Date of contract: December 31, 2010
Duration: 24 months
Amount: $ 842 965
TC-AQ: Quality management expert for Fruit Tree Productivity Project
Awarded to: ANTENOR
Date of contract: March 4, 2011
Duration: 3 months
Amount: $ 18 408
TC-D10.8: Expert in Market studies for Catalyst Fund
Awarded to: AGROCONCEPT
Date of contract: May 12, 2011
Duration: 2 months
Amount: $ 22 610
TC-D10.7: Expert for catalyst fund Procedures Manual
Awarded to: Mohammed ZIAD
Date of contract: May 13, 2011
Duration: 2 months
Amount: $22 359
TC-D10.5: Economist to coordinate the elaboration of Catalyst Fund proposal
Awarded to: Benabderraazik
Date of contract: May 18, 2011
Duration: 2 months
Amount: $35 011
TC-D10.6: Environmental Specialist
Awarded to: OUAZZANI
Date of contract: June 16, 2011
Duration: 2 months
Amount: $ 25 274
TC-3B2 bis : Irrigation infrastructure works
Awarded to: CAPEP
Date of contract: July 06, 2011
Duration: 15 months
Amount: $ 4 731 530
TC-3B3: Irrigation infrastructure works
Awarded to: Sté Sellam Azouz (Lot 8) ; SNCE (Lot 2 & 5)
Date of contract: July 06, 2011; July 19, 2011
Duration: 15 months
Amount: $ 10 392 730
TC-6B1: Refrigeration Equipments
Awarded to: SAMIFI MAROC
Date of contract: July 06, 2011
Duration: 120 days
Amount: $ 354 001
TC-6 A2 bis: Works of cleaning bundles of date palm tree for farmers in oasis areas
Awarded to: ARIG Travaux (Lots 1&3)
Date of contract: july 18, 2011
Duration: 18 months
Amount: $ 1 285 934
Total Fruit Tree Productivity Project: US $ 267 151 496
Small-Scale Fisheries Project
AF-1: Consultant to conduct EIA, Feasibility and design studies, Draft RFPs for AF-2 (Lot I + II + III), Provide oversight for AF-2
Awarded to: Groupement Conseil, Ingénierie et Développement (CID) and CRC SOGEMA Inc.
Date of the contract: February 3, 2009
Duration: 34 months
Amount: $ 15 985 145
AF-21: Consultant(s) to provide advice in sustainable development of fisheries
Awarded to: F. Henry from the enterprise Fisheries et Agriculture Economic Consulting
Date of the contract: June 30th, 2009
Duration: 08 months
Amount: $ 63 345
AF-1.2: Oversight Office in charge of technical studies regarding the optimization of plans and design memoranda, calculation and control of the construction of 20 fish landing sites, infrastructure in 13 fishing ports and 6 wholesale markets.
Awarded to: SOCOTEC MAROC
Date of the contract: July 1st, 2009
Duration: From the order of service until the final reception of all works.
Amount: $ 573 580
AF-5: Program design and baseline study for mobile fish vendors
Awarded to: Groupement AgriConsulting Maroc, AgriConsulting Europe, Planet Finance, and Cofrepêche
Date of the contract: September 29th, 2009
Duration: 09 months to be conducted over a 4-year period
Amount: $ 778 472
AF-20 Bis: Consultant(s) to provide advice in training of fishers
Awarded to: Meeransa Syed Shafee
Date of the contract: February 17th, 2010
Duration: 02 months
Amount: $ 28 917
AF-6: Training supports and training for ambulant fish vendors, whole sales managers and users
Awarded to: UNOPS
Date of the contract: February 18th, 2010
Duration: 44 months
Amount: $ 1 553 064
AF-7.1: Development of strategy of “AMP” for fishery objectives in Morocco
Awarded to: Agriconsulting Maroc/Agriconsulting Europe/Pescares Italia
Date of the contract: June, 8, 2010
Duration: 3 years & 2 months
Amount: $ 1 296 060
AF-8.1: Work construction Quick start
Awarded to: Gpt BUILNOR/URBAGEC (Lot 2), Gpt SUMC, JET ALU, MENASTEEL et SYSTHERM(Lot 3, Lot 5), Sté ENACODE (Lot 4)
Date of the contract: September 30, 2010
Duration: 12 months
Amount: $ 13 994 120
Total Small-Scale Fisheries Project: US $ 34 272 703.00
Artisan and Fez Medina
AFM-10: Consultant to conduct concept and market study for use of Makina site
Awarded to: AECOM International
Date of the contract: August 3rd, 2008
Duration: 09 months
Amount: $ 612 047
AFM-17: Consultant to conduct environment and social impact studies for Artisan Production Project Activity
Awarded to: Clean tech Environmental ressources Magament ERM
Date of the contract: March 31st, 2009
Duration: 04 months
Amount: $ 143 852
AFM-7B.2: Consultant to prepare TDR for the oversight AFM-7B-1
Awarded to: Amezian Hassani Hassan
Date of the contract: June 18th, 2009
Duration: 01 month
Amount: $ 14 767
AFM-7B (amended) : Consultant to conduct RAP for all sites in the Fez Medina, baseline ESIA studies for competition sites, Feasibility studies as input for competition sites, ESIA for all sites in the Fez Medina and Ain Nokbi, Implementation Oversight, etc.
Awarded to: Groupement Kilospace, Memoris, SCE and Team Maroc
Date of the contract: June 30th, 2009
Duration: 48 months
Amount: $ 2 2 225 635
AFM-10.1(amended): Economist to provide technical assistant to ADER in the implementation of AFM-10 contract
Awarded to: Naima Lahbil
Date of the contract: May 22nd, 2009
Duration: 06 months
Amount: $ 21 831
AFM-11B (amended): Consultant to manage architecture competition
Awarded to: Phase Eins
Date of the contract: December 7th, 2009
Duration: until June 30, 2011
Amount: $ 1 950 870
AFM-3B: Consultant to conduct a study to determine the promotion needs.
Awarded to: Groupement Aid to Artisans & Solimar
Date of the contract: February 12th, 2010
Duration: 07 months
Amount: $ 925 000
AFM-1: Consultant for artisan production project implementation
Awarded to: ATA/SOLIMAR
Date of the contract: March 1, 2010
Duration: 52 weeks
Amount: $ 1 848 000
AFM-7BC (amended): Technical assistance
Awarded to: Rachel Markowitz
Date of the contract: March 26, 2010
Duration: 6 months
Amount: $ 14 365
AFM-7B.1: Oversight office
Awarded to: SOCOTEC
Date of the contract: July 20, 2010
Duration: 3 years
Amount: $ 271 481
AFM-2P: Finalization of gas kilns financing procedures for AFM Project
Awarded to: OMAR ZAID
Date of the contract: August 18, 2010
Duration: 8 weeks
Amount: $ 19 284
AFM-11E: Agency to organize events & communication for architecture competition
Awarded to: PR Media
Date of the contract: September 02, 2010
Duration: 7 months
Amount: $ 174 602
AFM-7 Lab 01: Laboratory services (tests and analysis of materials)
Awarded to: LMGC
Date of the contract: September 01, 2010
Duration: 6 months
Amount: $ 122 850
AFM-7 Lab 02: Geothermal studies
Awarded to: G2 E SARL
Date of the contract: September 01, 2010
Duration: 6 months
Amount: $ 81 900
AFM-1K: Acquisition of Gas Kilns for demonstration
Awarded to: OZMAK Müh
Date of the contract: December 08, 2010
Duration: 5 months
Amount: $ 168 000
AFM-5A: Consultant for developing terms of Reference related to the Country Label for artisan products
Awarded to: ABDELHAK LOUBANE
Date of the contract: December 13, 2010
Duration: 2 months
Amount: $ 13 904
AFM-17M: Study of measures to reduce environnmental and social impact of “support for production”
Awarded to: CLEAN TECH
Date of the contract: December 22, 2010
Duration: 150 working days
Amount: $ 193 873
AFM-4A: Consultant for developing terms of reference related to publicity campaigns for craftsmen and “Small and Medium Enterprises-PME” in the artisan sector in the cities of Fez and Marrakech
Awarded to: Choukry Maghnouj
Date of the contract: December 30, 2010
Duration: 2 months
Amount: $ 11 752
AFM-6A: Consultant for developing terms of reference related to publicity campaigns for Fez and MarrakechMedina Tours, including artisan products
Awarded to: Choukry Maghnouj
Date of the contract: December 30, 2010
Duration: 2 months
Amount: $ 11 752
AFM-21: Consultant in legal and land tenure areas
Awarded to: Abdelhamid Bentahar
Date of the contract: October 15, 2010
Duration: 24 months
Amount: $ 74 262
AFM-10.2: Consultant services for management system for project sites
Awarded to: Ecoplannet
Date of the contract: June 16, 2011
Duration: 6 months
Amount: $ 42 812
Total Artisan and Fez Medina: US $ 8 942 839
Functional Literacy and Vocational training
AFM-31: Development of functional literacy training program and materials.
Awarded to: UNESCO
Date of the contract: February 11, 2010
Duration: 20 months
Amount: $ 750 000
AFM-30: Program management consultant (functional literacy, vocational training, competitive skills development program)
Awarded to: MSI
Date of the contract: May 6, 2010
Duration: 3 years & 3 months
Amount: $ 20 080 523
AFM-42: Edition and printing provisional teaching aids for the 1st cycle of functional literacy classes
Awarded to: Pantone Color’s SARL
Date of the contract: December 09, 2010
Duration: 2 weeks
Amount: $ 29 608
AFM-34: Curriculum development Consultant (Vocational training) in artisan sector
Awarded to: SFERE
Date of the contract: April 13, 2010
Duration: 11 months
Amount: $ 961 691
AFM-37: Technical assistance for developing communication strategy to promote functional literacy and vocational training in artisan sector
Awarded to: CRC SOGEMA
Date of the contract: April 27, 2010
Duration: 10 months
Amount: $ 336 579
AFM-41: Lodging and Conference rooms
Awarded to: Hotel Chellah & other suppliers
Date of the contract: March 2010
Duration: N/A
Amount: $ 22 717
AFM-44 Bis: Consultant for governance plan design of vocational training device in artisan sector
Awarded to: Abdellatif MOUTTAKI
Date of the contract: May 26, 2010
Duration: 5 months
Amount: $ 45 100
AFM-33: Technical assistance for developing communication strategy to promote functional literacy in Agriculture and Fisheries sector
Awarded to: CIDE
Date of the contract: July 19, 2010
Duration: 8 months
Amount: $ 220 000
AFM-36: Consultant to conduct training of Vocational trainers and Managers in artisan sector
Awarded to: DEMOS
Date of the contract: July 21, 2010
Duration: 24 months
Amount: $ 438 680
AFM-45 Ter: Consultant to support vocational training institution in their Institution Project elaboration
Awarded to: CO-EFFICIENCE
Date of the contract: July 28, 2010
Duration: 6 months
Amount: $ 24 088
AFM-32: Equipment of 130 functional literacy rooms in various regions
Awarded to: Maroc Bureau
Date of the contract: December 31 2010
Duration: 2 months
Amount: $ 295 957
AFM-35.6: IT Equipment for vocational training institution in artisanat sector
Awarded to: PC Memoria
Date of the contract: July 07, 2011
Duration: 2 months
Amount: $ 152 384
Total Functional Literacy & Vocational training: US $ 23 356 738
Financial Services
FS-1: Consultant to analyze regulatory and operational requirements for transformation of microcredit associations
Awarded to: DFC- Strategic Advisors and Project Managers for the Financial Sector
Date of the contract: August 26th, 2008
Duration: 09 months
Amount: $ 534 981
FS-3.1: Consultant for ESA training for AMC (Jaida Program) - Training Conception and preparation
Awarded to: Edic Sarl
Date of the contract: December 31st, 2009
Duration: 03 months
Amount: $ 161 635
FS-5.1: Needs assessment for the implementation of Management Information Systems in Microcredit Associations
Awarded to: HORUS Development Finance
Date of the contract: February 8, 2010
Duration: 03 months
Amount: $ 188 445
FS-3.2: Implemetation of ESA training
Awarded to: Edic ADI
Date of the contract: May 25, 2011
Duration: 12 months
Amount: $ 398 834
FS-5.11:Assessment for the implementation of Management Information Systems in RMS (Réseau de la Microfinance solidaire)
Awarded to: HORUS Development Finance
Date of the contract: June 06, 2011
Duration: 01 month
Amount : $ 24 440
Total Financial Services: US $ 1 308 335
Enterprise Support
ES-1: Capacity building of implementing entities of Enterprise Support Project
Awarded to: Cabinet Management Systems International (MSI)
Date of the contract: March 2nd, 2009
Duration: 24 months
Amount: $ 3 110 274
ES-3.1: Development and implementation of information system concerning enterprise support project
Awarded to: Wormitec
Date: November 24th, 2009
Duration: 06 months
Amount: $ 925 435
ES-2: Training for 400 Moukawalati enterprises and 200 income generating activities
Awarded to: TRIODOS FACET/Attitudes Conseil
Date of the contract: December 16th, 2009
Duration: 25 months
Amount: $ 7 705 775
ES-5H: Lodging and conference rooms
Awarded to: Miscellaneous Hotels
Date of the contract: March 2010
Duration: N/A
Amount: $ 927 974
ES-3.2: IT Equipments
Awarded to: ETCE Informatique ; SINERGYX
Date of the contract: August 23, 2010
Duration: N/A
Amount: $ 494 770
ES-4 bis: Study of business opportunities
Awarded to: SIS Consultant & Cabinet Gressard
Date of the contract: November 12, 2010
Duration: 30 months
Amount: $ 426 411
ES-5H3: Lodging and conference rooms
Awarded to: Hotel Kenzi Semiramis
Date of the contract: February 14, 2011
Duration: N/A
Amount: $ 46 950
ES-2 A: Evaluatin of Contract ES-2 administrative and financial management
Awarded to: Business Development Advisors Sarl
Date of the contract: July 06, 2011
Duration: 3 months
Amount: $ 20 381
Total Enterprise Support: US $ 13 657 969
Monitoring and Evaluation
ME-4(amended): Small Enterprise Support Impact Evaluation Design
Awarded to: Innovation for Poverty (IPA)
Date of the contract: May 13th, 2009
Duration: 33 months
Amount: $ 1 673 528
ME-5: Functional literacy and Vocational training
Awarded to: Saad Belghazi
Date of the contract: February 20th, 2009
Duration: 01 month
Amount: $ 52 481
ME-13A1: Consultant to realize 5 Training Modules in Relation to M&E Plan
Awarded to: Institut IDEA
Date of the contract: December 21st, 2009
Duration: 08 months
Amount: $ 179 223
ME-2A: identification and validation of (70) control perimeters
Awarded to: Groupement CID - SCET SCOM - ADI
Date: December 31st, 2009
Duration: 03 months
Amount: $ 151 968
ME-5B: Statistician - random sampling of rehabilitation perimeters for impact evaluation contract ME-2
Awarded to: Bruno Creppon
Date of the contract: March 5th, 2010
Duration: 01 month
Amount: $ 14 364
ME-5C (amended): Technical assistance for the use of software for operational operations (MS project) with the limits of logical approach
Awarded to: Promact
Date of the contract: December 31st, 2009
Duration of the contract: 02 months
Amount: $ 47 918
ME-1A: Baseline Survey - Agriculture
Awarded to: Agriconsulting
Date of the contract: February 25th, 2010
Duration of the contract: 09 months
Amount: $ 565 509
ME-2 (amended): Agriculture Impact Evaluation Design
Awarded to: NORC
Date of the contract: December 29th, 2009
Duration: until August 2013
Amount: $ 3 083 071
ME-6A: Requirements Definition for M&E MIS.
Awarded to: IT Consulting
Date of the contract: January 25th, 2010
Duration: 01 month
Amount: $ 41 925
ME-13B1: Lodging and conference rooms services for participant in ME-13 A-1 training
Awarded to: Golden Tulip Farah
Date of the contract: January 15th, 2010
Duration of the contract: N/A
Amount: $ 116 768
ME-13B1.1: Printing training documents
Awarded to: Intercopie
Date of the contract: March 16, 2010
Duration of the contract: N/A
Amount: $ 3 253
ME-6C.1: Conception, acquisition and putting into operation of the IT infrastructure for the APP information system
Awarded to: ECS Informatique
Date of the contract: March 24, 2010
Duration of the contract: 2 months
Amount: $ 85 862
ME-6C.2: Acquisition of MPMM: Methodology and project management
Awarded to: Softkey Technologies
Date of the contract: March 25, 2010
Duration of the contract: N/A
Amount: $ 4 811.39
ME-5E: Economic analysis of new activities planned in Fez medina activity rescoping
Awarded to: Hassan Benadberrazik
Date of the contract: March 28, 2010
Duration of the contract: 2 months
Amount: $ 14 364
ME-1B (amended): Baseline survey Small Scale Fisheries Project
Awarded to: AGRER N.V/CANAEST Consultores
Date of the contract: June 3, 2010
Duration of the contract: 5 months
Amount: $ 308 965
ME-13 A3: Participation in training
Awarded to: J-PAL Europe
Date of the contract: June 03, 2010
Duration of the contract: N/A
Amount: $ 1 875
ME-5G: Specialized translation of MCA Morocco monitoring and evaluation plan
Awarded to: Abdelaziz Sbai
Date of the contract: June 17, 2010
Duration of the contract: N/A
Amount: $ 4 958
ME-6A1: Definition of information system related to vocational training device of Secrétariat d’Etat Chargé de l’Artisanat (SECA)
Awarded to: Information Technology Consulting
Date of the contract: July 02, 2010
Duration of the contract: 5 weeks
Amount: $ 8 544
ME-12A: Value chain analysis (olive trees and date palms) in areas of project intervention "Fruit Tree"
Awarded to: PHYTO Consulting
Date of the contract: July 06, 2010
Duration of the contract: 6 months
Amount: $ 253 973
ME-7A: Car rental for baseline surveys
Awarded to: Fast-wave cars
Date of the contract: July 9, 2010
Duration of the contract: N/A
Amount: $ 40 388
ME-7A1: Printing documents
Awarded to: Intercopie
Date of the contract: July 16, 2010
Duration of the contract: N/A
Amount: $ 2 738
ME-6F: Acquisition and installation of splits
Awarded to: Sococlim
Date of the contract: July 16, 2010
Duration of the contract: N/A
Amount: $ 3 808
ME-13 A2: Capacity building of Directors and project coordinators in project management according to PMI standard
Awarded to: IDEA International
Date of the contract: August 12, 2010
Duration of the contract: 3 months
Amount: $ 89 250
ME-1C Bis: Baseline survey AFM Project
Awarded to: EDESAT
Date of the contract: August 18, 2010
Duration of the contract: 6 months
Amount: $ 274 272
ME-12C: Value chain analysis in “Small Scale Fisheries” project
Awarded to: COFREPECHE
Date of the contract: August 23, 2010
Duration of the contract: 6 months
Amount: $ 250 985
ME-5F: Assistance for impact assessment of Artisanat Project vocational training
Awarded to: Boujeema Mouflih
Date of the contract: August 27, 2010
Duration of the contract: 1 month
Amount: $ 12 587
ME-6 C4: IT Equipments
Awarded to: SINERGIX
Date of the contract: September 2, 2010
Duration of the contract: N/A
Amount: $ 219 179
ME-11: Audit of data base quality
Awarded to: INSTITUT IDEA INTERNATIONAL
Date of the contract: September 16, 2010
Duration of the contract: 17 months
Amount: $ 444 517
ME-12B: Analysis of almond and figs value chains in Fruit Trees Project areas
Awarded to: Gpt AGLAND Investment services/ FELLAH Conseil
Date of the contract: September 6, 2010
Duration of the contract: 8 months
Amount: $ 430 085
ME-7 A2: Car renting
Awarded to: Fast-Wave Cars
Date of the contract: October 28, 2010
Duration: 5 days
Amount: $ 3 121
ME- 15: Mid-term assessment of MCA-Morocco Program
Awarded to: Integration Ikesol
Date of the contract: November 01, 2010
Duration of the contract: 35 months
Amount: $ 839 800
ME-5D: Normalisation of MCA-Morocco work plans for the implementation of Program Management Information System
Awarded to: Gpmt M7 & Opteamar
Date of the contract: November 12, 2010
Duration of the contract: 5 weeks
Amount: $ 61 920
ME-6B: Design and implementation of MCA-Morocco Management Information System
Awarded to: Gpmt M7 & Opteamar
Date of the contract: November 12, 2010
Duration of the contract: 18 months
Amount: $ 270 000
ME-6C 5: Update of agro-economical database of MAPM
Awarded to: Creative Technologies
Date of the contract: November 16, 2010
Duration of the contract: 6 months
Amount: $ 102 333
ME-6G: equipment to connect APP annex with Information system
Awarded to: CBI
Date of the contract: November 16, 2010
Duration: 40 working days
Amount: $ 18 050
ME-5J: Individual Consultant for tender evaluation
Awarded to: Larbi Zagdouni/ Abdellah Ait Tihyaty
Date of the contract: December 6, 2010
Duration of the contract: 2 months
Amount: $ 17 624
ME-6H: Acquisition of STATA software
Awarded to: Softkey Technologies
Date of the contract: January 28, 2011
Duration of the contract: N/A
Amount: $ 17 918
ME-6C3: Extension of pilot phase of collection, transfer and dessemination of data on agricultural products
Awarded to: MEDI TELECOM
Date of the contract: February 3, 2011
Duration of the contract: by August 2013
Amount: $ 439 343
ME-1E: Baseline survey on Functional Literacy and Vocational Training activities in agricultural area
Awarded to: Fellah Conseil
Date of the contract: February 3, 2011
Duration of the contract: 4 months
Amount: $ 90 798
ME-6I: Personalisation of APP Intranet portal
Awarded to: Adil Elomari
Date of the contract: March 4, 2011
Duration of the contract: 1 month
Amount: $ 4 926
ME-4A: Development of Enterprise Support Project data base
Awarded to: IMP Consulting
Date of the contract: May 13 2011
Duration of the contract: 3 months
Amount: $ 21 982
Total Monitoring and Evaluation: US $ 10 268 981
APP’s Administration
ADM-1: Fiscal Agents services
Awarded to: GFA Consulting Group GmbH; Charles Kendall & Partners, Ltd.
Date of the contract: May 14th, 2008
Duration: 12 months of base period with a renewal option
Amount: $ 6 605 918
POA-1: Procurement Oversight Advisor/Agent Services
Awarded to: Crown Agents
Date of the contract: January 29th, 2009
Duration: 12 months of base period and 48 months of optional period
Amount: $ 6 794 671
ADM-41: Support on involuntary resettlement
Awarded to: Gordon Appleby
Date of the contract: June 23, 2010
Duration: 24 months
Amount: $ 130 000
ADM-31.2: Audit services
Awarded to: BDO
Date of the contract: July 28, 2010
Duration: 24 months
Amount: $ 128 548
ADM-45: Workshop 2010 Assessment and 2011 perspectives
Awarded to: Hotel TIKIDA Garden/ Hotel Villa du Lac
Date of the contract: October 26, 2010
Duration: 1 day
Amount: $ 11 205.02
ADM-44: Acquiqition of 4x4 vehicle for APP
Awarded to: Super Auto Distribution
Date of the contract: November 26, 2010
Duration: N/A
Amount: $ 146 467
COM- 9: Design and installation of stands at Salon Halieutis 2011
Awarded to: Cle Concept Communication
Date of the contract: January 20, 2011
Duration: N/A
Amount: $ 37 036.5
COM- 11: Blanket Purchase Agreement for the implementation of the institutional communication of APP
Awarded to: Cle Concept Communication
Date of the contract: March 29, 2011
Duration: N/A
Amount: $ 197 287
ADM-34.2 bis: Gender approach specialist
Awarded to: Abdelaziz Chaker
Date of the contract: January 28, 2011
Duration: 4 months
Amount: $ 18 679
ADM-34.3: Gender approach specialist
Awarded to: Carine Chevallier
Date of the contract: march 23, 2011
Duration: 3 months
Amount: $ 12 912
ADM-34.2: Gender approach specialist
Awarded to: Fatima Bakass
Date of the contract: March 3, 2011
Duration: 3 months
Amount: $ 26 782
ME-6J: Review of APP network
Awarded to: MTDS
Date of the contract: July 18, 2011
Duration of the contract: N/A
Amount: $7 327
ADM-34.4: Gender approach specialist
Awarded to: Carine Chevallier
Date of the contract: June 23, 2011
Duration: 7 months
Amount: $ 30 465
Administrative contracts: US $ 2 179 962.71
Administrative contracts of Project Management Units
TC-D8: Acquisition of vehicles for Fruit Trees Project
Awarded to: Global Engines Hyundai
Date of contract: May 03 2010
Duration: N/A
Amount: $ 53 350.48
TC-D9: Acquisition of broadcasting equipments
Awarded to: Micro Link
Date of contract: May 10, 2010
Duration: N/.A
Amount: $ 7 714.42
TC-10 D.1: 2 Consultants in agricultural engineer or civil engineer
Awarded to: Benchokroun ; KIC Sarlau
Date of contract: October 8, 2010
Duration: 30 months
Amount: $ 210 280.5
AF-D2: Technical Assistance (Public Private Partnerships)
Awarded to: VALYANS
Date of the contract: August 5, 2010
Duration: 18 months
Amount: $ 453 682
AF-D3: Office modification and maintenance (Small Scale Fisheries Project Management Unit)
Awarded to: Mimouza
Date of the contract: August 1st, 2009
Duration: 20 days
Amount: $ 37 594.00
AF-D4: Cabling works for IT and telephone connections for Small Scale Fisheries Project Management Unit
Awarded to: AZ-net
Date of the contract: August 1st, 2009
Duration: 20 days
Amount: $ 22 442.00
AF-D5: Office cleaning and security services for Small Scale Fisheries Project Management Unit
Awarded to: Casatechnique
Date of the contract: October 15th, 2009
Duration: 12 months
Amount: $ 13 050.00
AF-D11: Realization of the model of Beni Mellal wholesale fish market project
Awarded to: Les Maquettes d’Art
Date of the contract: April 04, 2010
Duration: N/A
Amount: $ 13 552.92
AF-D7: Assistance to UGP for the elaboration of Beni Mellal wholesale fish markets business plan
Awarded to: Salah AISSE
Date of the contract: June 22, 2010
Duration: 3 months
Amount: $ 26 813.70
AFM-D42: Acquisition of vehicles for PROJECT MANAGEMENT UNIT SECA
Awarded to: Global Engines Hyundai
Date of the contract: May 3, 2010
Duration: N/A
Amount: $ 53 350.48
AFM-FES-IT: IT Equipments
Awarded to: MicroLink
Date of the contract: July 16, 2010
Duration: N/A
Amount: $ 13 502.36
AFM-NG ADER: Office cleaning and security services for ADER
Awarded to: Ese Abderrahim Haroucha
Date of the contract: July 22, 2010
Duration: N/A
Amount: $ 9 962.70
AFM-FES-V: Acquisition of vehicles for ADER FES
Awarded to: Ets HAKAM FRERES; Global Engines Hyundai
Date of the contract: July 28, 2010
Duration: N/A
Amount: $ 50 289.49
AFM-FES HR: Recruitment office for AFM ADER
Awarded to: CV Search
Date of the contract: August 4, 2010
Duration: 12 months
Amount: $ 36 195.30
AF-D12: Architect technical assistance
Awarded to: Fadel GUERRAOUI
Date of the contract: December 22, 2010
Duration: 18 months
Amount: $ 91 833
AF-D14: Recruitment Office for Small Scale Fisheries Project Management Unit
Awarded to: CV Search
Date of the contract: December 20, 2010
Duration: 24 months
Amount: $ 23 107.9
AFM-FEZ AD1: Acquisition of IT Equipment and furniture
Awarded to: Socobano; Microlink; TRAREM
Date of the contract: October 27, 2010
Duration: N/A
Amount: $ 58 818.60
AFM-40: Acquisition of software for UGP ADER FEZ
Awarded to: Robobat Afrique/ Interface Computer
Date of the contract: October 27, 2010
Duration: N/A
Amount: $ 67 215
TC-5A2 S: Renting of 2 stands for APP participation in SIAM 2011
Awarded to: SIAM
Date of the contract: April 1, 2011
Duration: N/A
Amount: $ 21 246
AF-D15: IT Equipment
Awarded to: RABATECH
Date of the contract: April 06, 2011
Duration: 2 months
Amount: $ 3 478
AF-D17: Acquisition of vehicles
Awarded to: Intercontinental (Lot 1) and Hyundai (lot 2)
Date of the contract: July 18, 2011
Duration: 6 months
Amount: $ 70 034
AF-D21: Procurement Consultant
Awarded to: Nazha Talmi
Date of the contract: July 18, 2011
Duration: 6 months
Amount: $ 24 075
AFM-D43: Notary services
Awarded to: Me Loutfi and Me Sadoq
Date of the contract: June 16, 2011
Duration: 24 months
Amount: $ 199 999.8
AFM-FEZ Autodesk: Acquisition of software
Awarded to: GEOMAPGIS
Date of the contract: April 18,, 2011
Duration: N/A
Amount: $ 18 006
AFM-FEZ Cablage: Cabling works for IT and telephone connections
Awarded to: NARJISS SOFT
Date of the contract: May 09, 2011
Duration: N/A
Amount: $ 11 545
TC-5 A2S2: Building of SOUK Stand (SIAM 2011)
Awarded to: Ateler K
Date of contract: April 22, 2011
Duration: N/A
Amount: $ 16 046
TC-UGP Vehicle: Acquisition of vehicles
Awarded to: Société Générale d’Automobile
Date of the contract: July 07, 2011
Duration: N/A
Amount: $19 107
TC-UGP Bureau: Office Equipment and IT Equipment
Awarded to: COMABU
Date of the contract: July 08, 2011
Duration: N/A
Amount: $5 113
Total APP Administration: US $ 17 958 664.88
TOTAL of all Contracts: US $ 376 917 725.88
N.B. The list of contracts signed by APP does not include contracts for administrative purposes and amounts committed by way of Grants

The Millennium Challenge Corporation (MCC) is a bilateral US foreign aid agency established in 2004 by the United States Congress as an autonomous agency of the State Department and USAID.
It offers grants to nations that are assessed to have good economic policies and the potential for economic development. The nation qualification procedure is objective, comprising third-party scores in 17 different fields and any country that qualifies must apply for a grant with a specific project in mind.
MCC was founded on the concept that help is most effective when it strengthens good government, economic freedom and investments in people.
Covers formal and informal education, training, and capacity-building activities that develop knowledge, skills, and institutional capabilities across all age groups.
Focuses on protecting natural ecosystems, promoting sustainable resource management, enhancing climate resilience, and mitigating the impacts of climate change through conservation, adaptation, and low-carbon initiatives.